Math 1.0 Verf
From DDCIDeos
(Redirected from Math Verf)
Verification project for the 1.0.x Math library for MIPS and PPC.
Description
It will support GCC 4.6.1 and MIPS and correct a number of PCRs.
The 1.0.x Math library is hosted in the Fourpeaks distribution.
Useful Links
- Query of all outstanding PCRs
- mainline review status
Status
We're verifying mainline, closing defect and a few enhancement PCRs.
Trace Matrix Warnings
None.
Issues/Concerns
None.
Test global issues
Add -passive=true to /desk/bin/test-component.py around line 314 for tests to run on qemu-mips under Windows 7.
Test Team Needs Guidance
Math Library Cert Work
| Initialize Status Files | Done | |
| Requirements review | Done | |
| Code review | Done | |
| Test Case Development | Done | |
| Test Procedure Development | Done | |
| Test Reviews | Done | |
| Software life cycle audits | Done | |
| ABC SCAT Qual | Done | |
| Integration Review | Done | |
| Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed | ||
|---|---|---|
| Formal build (including Conformity inspection) | Done | |
| Before the following can be done the Formal build needs to be completed | ||
| Executable Object Code Analysis | ||
| Requirements Coverage Analysis | Done | |
| Before the following can be completed all of the above analysis need to be completed | ||
| Run For Score | Done | |
| - Test Results Review | Done | |
| Before the following can be done the Run For Score needs to be completed | ||
| Structural coverage analysis | Done | |
| Verification audit | KL | Done |
| Before the following can be done the B-Tree analysis and Run For Score needs to be completed | ||
| Stack analysis | Not Applicable | |
| Before the following can be completed all of the above tasks need to be completed | ||
| Back end Docs | ||
| - SLCECI | Done | |
| - SLCECI review | Done | |
| - SCI | Done | |
| - SCI review | Done | |
| - Open Problem Reports List | Done | |
| - SAS | Done | |
| Populate the cert archive | Done | |
| Software conformity audit | Done | |
| Before the new baseline can be released the following must be completed | ||
| Capsule release of Math x86 with header files moved | Done | |