Weekly Status Meetings

2010-10-13

Attendees

  • Matt Diethelm (DDC-I)
  • Ole Oest (DDC-I)
  • Martin Beckmann (Septentrio)
  • Filip Verhaeghe (Septentrio)

Minutes

DDC-I presented technical progress to date on Septentrio Basic BSP.

DDC-I presented the idea that it could update the Embedded Planet 8343 Eval Board BSP and provide that update to Septentrio sometime in early November; however doing so would delay the initial Septentrio BSP by one week to 19-Dec-2010.

  • Septentrio listed problems they were having with their DDS distribution (DDS20100729):
    • Unsuccessful uninstall using uninstaller program
    • Now having target connection problems
    • Now having java out of memory messages
    • Now having general protection faults

Actions

  • Septentrio would like the name of a DDS technical support person they can contact.
  • Septentrio would like Martin Beckmann to be CC'ed on any email correspondence.
  • Septentrio to decide whether DDC-I is to move forward on an EP8343 Eval board update for them. (Filip will handle this)
  • DDC-I to instruct Septentrio on how to increase the amount of Deos RAM available on the Embedded Planet board. (Assigned to Matt)
Release Schedule
  • Basic BSP - Due 12-Dec-10; estimated delivery TBD
Schedule Detail

See the excel spreadsheet.

Projects

7.6.1 kernel Cert Work

Task
Assignment
Status
Test Reviews Bill, Gary, Karl, Ryan Done
ABC SCAT Qual Ryan Done
Portal Analysis Gary Done
V-Table Analysis Bill Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) Ryan Done
Before the following can be done the Formal build needs to be completed
Executable Object Code Analysis Note: The howto needs some work here.
- linker invariants Analysis Gary "Done"
- ppc stwcx. instruction Analysis Bill Done
- BIT RAM tests Analysis Aaron Done
- BIT RAM decode tests Analysis Aaron Done
- Required Pad Pool Analysis Bill Done
- Startup CRC Analysis Bill Done
B-Tree analysis Karl Done
Review of above. Gary Done
Requirements Coverage Analysis Karl Done
Before the following can be completed all of the above analysis need to be completed
Run For Score Ryan Done
- Test Results Review Bill Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis Aaron & Ryan Done
Before the following can be done the B-Tree analysis and Run For Score needs to be completed
Stack analysis Ryan Done
Before the following can be completed all of the above tasks need to be completed
Back end Docs
- SLCECI Adina Done
- Review of above Gary Done
- SCI Adina Done
- Review of above Gary Done
- Open Problem Reports List Ryan Done
- SAS Gary (construct the draft) Done
SAS requires a note about non-support of non-CLFLUSH processors
Populate the cert archive Adina Done


Milestones Due Date Estimated Delivery Delivered Percentage Complete
[1] Startup Full Functionality Release 08-FEB-10 04-JAN-10 TBD 19%
[2] Startup Test Cases and Procedures TBD TBD TBD TBD
[3] Startup Verified Release 14-APR-10 16-MAR-10 TBD 0%


Milestones Due Date Estimated Delivery Delivered Percentage Complete
[1] EP8343M BSP 11-NOV-09 18-JAN-10 18-JAN-10 100%


Milestones Due Date Estimated Delivery Delivered Percentage Complete
[1] Stella Boot Full Functionality 14-JUL-10 17-DEC-10 17-DEC-10 100%
[2] Stella Boot Verf Release 20-APR-11 TBD TBD 0%


Milestones Due Date Estimated Delivery Delivered Percentage Complete
[1] Stella PAL Full Functionality 14-JUL-10 17-DEC-10 17-DEC-10 100%
[2] Stella PAL Verf Release 20-APR-11 TBD TBD 0%