CLCM Support Project

From Deos
Jump to navigationJump to search


The Closed Loop Control Module (CLCM) support project is part of the CLCM_Program.

Description

The Deos team has been tasked to support the CLCM engineers' development and debug efforts by supplying technical support and design consulting.

News

  • 2007-01-09 - User:Matt.diethelm@honeywell.com CLCM team has been disbanded. This is not likely going to be resurrected. I'm marking our involvement complete.
  • 2006-08-07 - [1] "Our CLCM project has been budget-cut out of existence on Friday. Therefore, please don't expend any additional $$ on our requested DEOS change (ability to raise an interrupt from one process to another) unless I notify you that our status has changed again."
  • 2006-07-16 - Project page created.

Tasks

Initial Budget: $12,700

YTD: $6,223

Current ETC: $3,777

Current EAC: $10,000

Milestones Due Date Estimated Delivery Delivered Percentage Complete
Level of Effort Support 31-DEC-2006 31-DEC-2006 N/A 63%


Note: Unless noted otherwise, all estimates are in terms of effort hours.

Support

This is a level of effort task. Various Deos team members may be asked to assist with any technical issues as well as provide guidance. The hours spent doing that should be accumulated here in order for us to see how much we're spending.

Original Estimate Current Estimate Elapsed Remaining
78 78 49 29

Timesite Administrivia

See Timesite_Codes