Internet API Library Project

From Deos
Jump to navigationJump to search


Description

This project defines the work required to add the ability to test for and explicitly handle multi-line FTP server replies as documented in PCR:4009.

News

  • 2007-01-09: From User:Matt.diethelm@honeywell.com: Customer has worked around the problem without requiring Inet API library change. Marking this project complete.
  • 2006-09-21: From Jack Rahn: "Short-term plan is to remove the CMC database validation request, thereby removing the source of the problems. This is an IDS impact only. Will follow up with a summary later - undetermined how to proceed long term (e.g. DEOS). Thanks to everyone who supported this activity!"
  • 2006-09-20: This project has not been approved or funded. It exists to provide the information necessary for our customers to determine whether to pursue the option of having the Internet API Library updated.

Tasks

Initial Budget: $77,216 (Based on a 2006-Sep-21 baseline estimate of 608 hours)

YTD: $0

Current ETC: $77,216

Current EAC: $77,216

Milestones Due Date Estimated Delivery Delivered Percentage Complete
Inet API Library 2.0.2 verified TBD TBD TBD 0


Note: Unless noted otherwise, all estimates are in terms of effort hours.

Internet API Library Updates

Task Assignee Risk Original Estimate Current Estimate Elapsed Remaining
Requirements development TBD TBD 40 40 0 40
Code development TBD TBD 80 80 0 80
Test development TBD TBD 120 120 0 120
Requirements review TBD TBD 40 40 0 40
Code review TBD TBD 40 40 0 40
Test review TBD TBD 80 80 0 80
Software life cycle audit TBD TBD 16 16 0 16
Requirements coverage analysis TBD TBD 40 40 0 40
Structural coverage analysis TBD TBD 40 40 0 40
Conformity inspection (SQA witness of certification build) TBD TBD 8 8 0 8
SCAT/ABC qualification TBD TBD 8 8 0 8
Integration review TBD TBD 8 8 0 8
Run for score, including SQA witnessing, and test results review TBD TBD 8 8 0 8
Verification audit TBD TBD 16 16 0 16
Certification documents: SAS, SLCECI, SCI TBD TBD 40 40 0 40
Population of certification archive TBD TBD 8 8 0 8
Software conformity audit TBD TBD 16 16 0 16
Totals 608 608 0 608

Timesite Administrivia

Project is not approved. No Timesite Code to charge.