Internet API Library Project
From Deos
Jump to navigationJump to search
Description
This project defines the work required to add the ability to test for and explicitly handle multi-line FTP server replies as documented in PCR:4009.
News
- 2007-01-09: From User:Matt.diethelm@honeywell.com: Customer has worked around the problem without requiring Inet API library change. Marking this project complete.
- 2006-09-21: From Jack Rahn: "Short-term plan is to remove the CMC database validation request, thereby removing the source of the problems. This is an IDS impact only. Will follow up with a summary later - undetermined how to proceed long term (e.g. DEOS). Thanks to everyone who supported this activity!"
- 2006-09-20: This project has not been approved or funded. It exists to provide the information necessary for our customers to determine whether to pursue the option of having the Internet API Library updated.
Tasks
Initial Budget: $77,216 (Based on a 2006-Sep-21 baseline estimate of 608 hours)
YTD: $0
Current ETC: $77,216
Current EAC: $77,216
| Milestones | Due Date | Estimated Delivery | Delivered | Percentage Complete |
|---|---|---|---|---|
| Inet API Library 2.0.2 verified | TBD | TBD | TBD | 0 |
Note: Unless noted otherwise, all estimates are in terms of effort hours.
Internet API Library Updates
| Task | Assignee | Risk | Original Estimate | Current Estimate | Elapsed | Remaining |
| Requirements development | TBD | TBD | 40 | 40 | 0 | 40 |
| Code development | TBD | TBD | 80 | 80 | 0 | 80 |
| Test development | TBD | TBD | 120 | 120 | 0 | 120 |
| Requirements review | TBD | TBD | 40 | 40 | 0 | 40 |
| Code review | TBD | TBD | 40 | 40 | 0 | 40 |
| Test review | TBD | TBD | 80 | 80 | 0 | 80 |
| Software life cycle audit | TBD | TBD | 16 | 16 | 0 | 16 |
| Requirements coverage analysis | TBD | TBD | 40 | 40 | 0 | 40 |
| Structural coverage analysis | TBD | TBD | 40 | 40 | 0 | 40 |
| Conformity inspection (SQA witness of certification build) | TBD | TBD | 8 | 8 | 0 | 8 |
| SCAT/ABC qualification | TBD | TBD | 8 | 8 | 0 | 8 |
| Integration review | TBD | TBD | 8 | 8 | 0 | 8 |
| Run for score, including SQA witnessing, and test results review | TBD | TBD | 8 | 8 | 0 | 8 |
| Verification audit | TBD | TBD | 16 | 16 | 0 | 16 |
| Certification documents: SAS, SLCECI, SCI | TBD | TBD | 40 | 40 | 0 | 40 |
| Population of certification archive | TBD | TBD | 8 | 8 | 0 | 8 |
| Software conformity audit | TBD | TBD | 16 | 16 | 0 | 16 |
| Totals | 608 | 608 | 0 | 608 | ||
Timesite Administrivia
Project is not approved. No Timesite Code to charge.