Kernel 7.2.3 Project

From Deos
Jump to navigationJump to search

Project to track status and features for the 7.2.3 kernel certification

Tasks

Initial Budget: TBD

TTD: 409 Hours + Toronto PO

Current ETC: hours

Current EAC: hours

Non Labor:


Useful Links

The PCRs are categorized below for estimation purposes.





Delivery Due Date Estimated Delivery Delivered Percentage Complete
[1] Finish Test Reviews Complete 29-OCT-2009 1-NOV-2009 20-OCT-2009 100%
[2] Test Infrastructure Complete 8-NOV-2009 1-NOV-2009 ' 80%
[3] Preliminary Software Accomplishment Summary Release 15-DEC-2009 08-DEC-2009 TBD 0%
[4] Final Software Accomplishment Summary Release 22-JAN-2010 22-JAN-2010 TBD 0%



Delivery [1]. Test Reviews Complete.

Task Dependency Assignee Risk Notes Original Estimate Current Estimate Elapsed Remaining
[1.0] Review 190 remaining files   JK,SPS,CP,GCj,UK   New task.
{4}
475 475 270 204
Totals  475 475 271 204




Tasks for Delivery [2]. Test Infrastructure complete

Task Dependency Assignee Risk Notes Original Estimate Current Estimate Elapsed Remaining
[2.0] Testsuite: HPC2 platform ported to lwIP. none CP,UK None Side task because reviews went well 80 40 40 0
[2b.1] Testsuite: AMD Geode platform ported to lwIP. none CP None PO provided by Toronto 80 40 40 0
Totals  160 80 80 0


Delivery [3]: Preliminary Software Accomplishments Summary Release.

Post Development and Review Cert Activities

The following is the estimate for all certification activities that occur post development and review. This is a constant cost no matter how large the kernel source change. Note: Unless noted otherwise, all estimates below are in terms of effort hours.

Task Dependency Assignee Risk Notes Original Estimate Current Estimate Elapsed Remaining
[3.1] Update Agave 7.1. SAS per PCRs and comments from users 2b.4 GCJ None   40 40 20 20
[3.2] Review Agave 7.1. SAS C.0.0 UK, GCJ None   24 24 9.5 14.5
[3.3] Preliminary 7.2.3 SAS C.0.0 SPS None   24 24 18 6
[3.3] Review Preliminary 7.2.3 SAS C.0.0 SPS,GCJ None   24 24 9.5 14.5

Delivery [4]: Software Accomplishments Summary Release.

Post Development and Review Cert Activities

The following is the estimate for all certification activities that occur post development and review. This is a constant cost no matter how large the kernel source change. Note: Unless noted otherwise, all estimates below are in terms of effort hours.

Task Dependency Assignee Risk Notes Original Estimate Current Estimate Elapsed Remaining % Complete
[4.0.0] Software life cycle audit #1 (See Note 1) 2b.4 KL None   24 24 8 0 100
[4.0.2] Process Non-Compliance C.0.0 UK, SPS None   40 40 0 0 100
[4.1] B-Tree Analysis 2 CP, AL None See also PCR:563 40 5 5 0 100
[4.2] Executable object code analysis 2b.4 CP, AL, JK None See also PCR:2036. Includes analysis of PCR:6219. 32 161 161 0 100
[4.3] Hash Probability Analysis 2b.4 JK,AL None Now obsolete; see PCR:6201 8 5 5 0 100
[4.4] Portal Analysis 2b.4 SPS None   16 10 10 0 100
[4.5] Requirements coverage analysis 2b., 4.2 JK,SPS None 32 0 6 0 100
[4.6] Vtable Analysis 2b.4 SPS None   32 12 12 0 100
[4.7] Conformity inspection - SQA build Witness (See Note 1) 2b.4 KL, SPS, UK None   8 8 6 0 100
[4.8] SCAT/ABC qualification 2b.4 UK None   8 11 11 0 100
[4.8.1] Compiler assessment for PPC and X86 2b.4 JK None   0 24 24 0 100
[4.9] Integration review 2b.4 CP,UK,KL None   8 8 8 0 100
[4.10.1] MPC7448 Run for score, including SQA witnessing, and test results review (See Note 1) 2b.4 UK, KL None   8 36 36 0 100
[4.10.2] AMD Geode Run for score, including SQA witnessing, and test results review (See Note 1) 2b.4 CP, KL None   8 16 16 0 100
[4.11.1] PPC Structural coverage analysis C.7.1 JK None Includes new version of ABC/SCAT, kernel rebuild 32 145 145 0 100
[4.11.2] X86 Structural coverage analysis C.7.2, C.8.1 JK None   32 60 60 0 100
[4.12] Verification audit (See Note 1) C.8.2 KL None   8 8 6 0 100
[4.13] Process Non-Compliance C.9 GCJ, KL None   40 0 0 0 100
[4.14] Open Problem Reports List C.9.1 JK None   20 13 13 0 100
[4.15] SAS, SLCECI, SCI C.10.0 GCJ, JK, UK None 60 60 41 0 100
[4.16] Population of certification archive (PCA) C.10 GCJ, JK None   8 12 12 0 100
[4.17] Software conformity audit (See Note 1) C.11 KL None   8 8 8 0 100
Totals  472 666 593 0 100

Note 1: The SQA activity related to this item is project specific (according to the SQAP). According to the independence requirement (defined on 02/14/2007) the person that performs this role cannot have been involved in any of the development, verification, or configuration management activities for that project, except as needed to complete the activities of the SQA process.