SCC Driver Certification Support Project

From Deos
Jump to navigationJump to search


The Toronto SEPDS engineering staff is porting our certified FCCenet partitioned ethernet driver to work on their SCC hardware.

Description

The Deos team is providing certification process oversight and technical consulting for the SCC port of our FCCenet software component. HTSL is doing the port under direction of the Toronto SEPDS program office (Chris Southern). This is all in support of the SEPDS_Program.

News

  • 2006-08-17: This project appears to be no longer active.
  • 2006-05-18: From User:Matt.diethelm@honeywell.com: The SCC Run For Score appears to have happened. The SQA log now shows that an RFS witness has been performed.
  • 2006-04-18: From User:Cassandra.fleetwood@honeywell.com: "...$6,215 remained after the final invoice on SEPDS PO 742620. In order to use the balance, Toronto has to decrease the previous PO to the amount invoiced and issue a new PO for the remaining amount (and any additional amount they want to add). The new PO has to be issued to our new organization (Electronic Software COE, Operating Systems)..."
  • Checking on funding source. Last known source was 2005 SEPDS (Toronto) PO 742620 for $500K (Project Number D12023).
  • 2006-04-12 - HTSL is struggling with following the Deos certficiation process. A telecon for 2006-04-13 has been scheduled.

Tasks

Initial Budget: $20,320

YTD: $8,636

Current ETC: $11,684

Current EAC: $20,320

Note: Unless noted otherwise, all estimates are in terms of effort hours.


HTSL Support

This is a level of effort task. Various Deos team members may be asked to assist The SEPDS SCC team with any technical issues as well as provide guidance on following the Deos certification process and procedures. The hours spent doing that should be accumulated here in order for us to see how much we're spending.

We've estimated a level of effort of 4 hours per week beginning March, 2006 and concluding at the end of 2006.

  • RISK: If HTSL can't complete the work, the Deos team may then become responsible for finishing the effort. Also, if HTSL cannot adequately defend their artifacts, the Deos team would also become responsible for ensuring a successful audit.
Original Estimate Elapsed
160 68

Timesite Administrivia

See Timesite_Codes