SQA Project

From Deos
Jump to navigationJump to search

The purpose of this project is to facilitate the transition of Deos SQA to ALT Software

Description

The SQA activities which need to be performed, as well as their frequencies, can be found in Software Quality Assurance Plan for Deos, DEOSDOC4.

Contacts

ALT Contact: John Jarvis - 416-203-8508
ALT Financial Contact: Don Joncas - 416-203-8508
Deos Technical & Program Contact: Paul Self - 727-539-4751
Deos Financial Contact: Lisa Bratlien - 602-436-7456

Tasks

Initial Budget: 320 hours (Negotiated by B.Cronk; the budget was re-evaluated and renegotiated by R.Lewis to 775 hours based on projected hours by project)

YTD: 0 hours

Current ETC: 0 hours

Current EAC: 0 hours


Milestones Due Date Estimated Delivery Delivered Percentage Complete
SQA Activities (LOE) 1-Aug-2008 1-Aug-2008 TBD 44%


SQA Activities (LOE) Tasks

Task Dependency Assignee Risk Original Estimate Current Estimate Elapsed Remaining
SQA Activities (LOE) None ALT Employee None 775 775 342 433

Standards

SQA Activities

All SQA activities will be performed in compliance with: Software Quality Assurance Plan for Deos, DEOSDOC4 as well as all documents it references.

Organizational Responsibilities

Honeywell Responsibilities

Provide project coordination within Honeywell between departments and between Honeywell and ALT Software.

Product Engineering

  • Review project scope and schedule with ALT Software.
  • Provide access to the software tools required to develop and test the course material (i.e., examples & exercises).
  • Provide a Technical Lead to work with ALT Software during project.

Note: It is expected that Honeywell will provide the technical lead on this project and will aid the ALT Software's engineers on this task. The technical lead's role is to serve as the project's overall architect and arbitrator. ALT Software will make every effort to minimize the technical lead's involvement, but will need their assistance and guidance in order to ensure a successful completion to the project.

Software Configuration Management

  • Maintain Configuration Management.
  • The Honeywell Technical Lead will be responsible for this activity.

Honeywell Program Management Responsibilities

The work responsibilities of Honeywell Program Management are as follows:

  • Facilitate the authorization of statements of work and quotes
  • Facilitate changes to statements of work
  • Provide purchase orders and payment authorization

ALT Software Responsibilities

  • ALT Software will provide status to Honeywell upon request.
  • Progress report should be submitted to Honeywell Technical Lead at a rate to be determined by said lead.

Note: above progress should be measured against incremental, achievable milestones rather than percentage complete. Progress reports will consist of the statement that we achieved the milestone, didn't achieve the milestone (and what we will do to mitigate), or the milestone has changed.