AFDX Antero Project

From DDCIDeos
Jump to navigationJump to search

2115-320-601; "A" Tasks
Integrate AFDX into our commercial offering.

Description

This project will, at a minimum, integrate the AFDX infastrucutre into DDS. At a maximum, it will establish a new verified baseline of the AFDX infastrucutre with the limitations removed.

Status

Milestones Due Date Estimated Delivery Delivered Percentage Complete
[1] AFDX Current Functionality 10-JAN-10 25-Nov-09 25-Nov-09 100%
[2] AFDX No Limitation 08-FEB-10 08-FEB-10 08-FEB-10 80%
[3] AFDX Verf Release 12-JUL-10 TBD TBD 0%

[2] Updated code and tooling was delivered on 8-Feb-10. Requirements and test updates are needed prior to verf activities.


[3] AFDX Verf Release

Task Dependency Assignee Original Estimate Elapsed Remaining
3.1 Energize Review Status Files 1.5 Mike 27 0 27
3.2 Requirements review 1.5 Mike 14 0 14
3.3 Code review 3.2 Karen 14 0 14
3.4 Test Case Development 1.5 Mike 20 0 20
3.5 Test Case Review 3.2 & 3.4 Karen 68 0 68
3.6 Test Procedure Development 1.5 Mike, Karen 393 0 393
3.7 Test Procedure Review 3.5 & 3.6 Mike, Karen 34 0 34
3.8 Software life cycle audit 3.7 Kelly 24 0 24
3.9 Requirements coverage analysis 3.7 Karen 7 0 7
3.10 Conformity inspection - SQA build Witness 3.9 Kelly, Karen 8 0 8
3.11 SCAT/ABC qualification None Mike 14 0 14
3.12 Integration review 3.10 & 3.11 Kelly, Karen 7 0 7
3.13 Run for score, including SQA witnessing, and test results review 3.12 Kelly, Karen 8 0 8
3.14 Structural coverage analysis 3.13 Mike 58 0 58
3.15 Verification audit 3.14 Kelly 12 0 12
3.16 Open Problem Reports List 3.13 Karen 8 0 8
3.17 SAS, SLCECI, SCI 3.16 Mike, Karen 28 0 28
3.18 Population of certification archive (PCA) 3.17 Mike 32 0 32
3.19 Software conformity audit 3.18 Kelly 8 0 8
Totals 783 0 783

AFDX Library mainline review status

AFDX Driver mainline review status