ANSI Jupiter

From DDCIDeos
Jump to navigationJump to search

ANSI library updates for Desert_Eagle_Program. This is a follow on to ANSI Multicore.

A DAL A project.

This page tracks development and verification activities and progress.

Deos_Desert_Eagle_D2_Release is unverified.

The final release will be verified (at least for ARM).


Customer Programs

This component is expected to be used by the following programs:


Scope

The project calls for ANSI to be extended with the following APIs:

  • free() and malloc_stats()

Design Notes

PCR 14325 added to address math with sizeof(size_t) in FP XML (integration tool)

Activities

Outstanding Questions to Customer

  • TBD

Outstanding Requirement Tasks

  • TBD

Outstanding Code Tasks

  • TBD

Outstanding Test Tasks

  • TBD


Task
Assignment
Status
Create and Initial Population of Certification Archive (If already created, just perform populate step.) CP Done
Requirements Development CP/JON Done
Standards Change Analysis CP Done
Architecture Change Impact Analysis CP Done
Initialize Status Files Complete Standards Change Analysis first. CP Done
Requirements review RDR Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. CP Done
Code review RDR Done
Check/correct EOL on desk installed components to LF & verify other config files are not native. CP Done
Test Case Development CP/RDR Done
Test Procedure Development CP/RDR Done
Test Reviews Notify SQA when this activity is complete. DD/RDR Done
Software life cycle audits JEC Done
ABC SCAT Qual JON Done
Before the following can be done the above activities must be complete
Integration Review JON Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) JON/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence)
Executable Object Code Analysis Review (Testing vs Release variant equivalence)
Requirements Coverage Analysis JON Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score JON/JEC Done
Test Results Review JON Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis JON Done
Floating-point Analysis JON Done
Before the following can be completed all of the above tasks need to be completed
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive JON Done
Report Documents
- SLCECI JON Done
- SLCECI review KKL Done
- SCI JON Done
- SCI review KKL Done
Open Problem Reports List (after the final CCB) JON Done
- SAS JON Done
- SAS review KKL Done
- Publish Backend Docs: (update analysisStatus.txt) KKL Done
Update /11-14-verf-results/analysis/change-impact/analysisStatus.txt once verification completes on dependencies to include final change-impact analysis Update Change-Impact Analysis JON Done
Software conformity audit - Will finish once analyses above are finalized JEC Done
Final Steps upon Verf Complete KKL Done