CFFS-SATA-ATAPI verification for Celestial Program.

A DAL A project.

This page tracks development and verification activities and progress.

Charge Code

Server verification being tracked under Celestial in Project Manager.

Scope

Initial verification of cffs-sata-atapi for Program_Celestial

Activities

Task
Assignment
Status
Create and Initial Population of Certification Archive (If already created, just perform populate step.) JMK/JC Done
Requirements Development JMK Done
Standards Change Analysis Complete before Initializing Status Files. JMK Done
Architecture Change Impact Analysis JMK Done
Initialize Status Files Complete Standards Change Analysis first. JMK Done
Requirements review SLeon Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. JMK Done
Code review JJK Done
Check/correct EOL on desk installed components to LF & verify other config files are not native. JMK Done
Test Case Development SLeon Done
Test Procedure Development JMK Done
Test Case Reviews JMK Done
Test Procedure Reviews Notify SQA when this activity is complete. SLeon Done
Software life cycle audits JEC Done
ABC SCAT Qual SLeon Done
Before the following can be done the above activities must be complete
Integration Review SLeon Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and ABC Qual need to be completed
Formal build (including Conformity inspection) SLeon/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence) N/A Done
Executable Object Code Analysis Review (Testing vs Release variant equivalence) N/A Done
Requirements Coverage Analysis SLeon Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score SLeon/JEC Done
Test Results Review SLeon Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis SLeon Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive SLeon Done
Report Documents
- SLCECI SLeon Done
- SLCECI review KKL Done
- SCI SLeon Done
- SCI review KKL Done
Open Problem Reports List (after the final CCB) SLeon Done
- SAS SLeon Done
- SAS review KKL Done
- Publish Backend Docs: (update analysisStatus.txt) KKL Done
Software conformity audit JEC Done
Final Steps upon Verf Complete KKL Done