CFFSAPI653P2 Kismet

From DDCIDeos
Jump to navigationJump to search

CFFSAPI653P2 verification for Throne. A DAL A project.

This page tracks development and verification activities and progress.


Charge Code

P2 API verification being tracked under Throne in Project Manager.

Scope

Activities

Task
Assignment
Status
Create and Initial Population of Certification Archive (If already created, just perform populate step.) JEC Done
Requirements Development SPS Done
Standards Change Analysis MAS Done
Architecture Change Impact Analysis SPS Done
Initialize Status Files MAS Done
Requirements review RDR In Work
Code Development, i.e. trace tag insertion and additional test points as determined via test development. SPS In Work
Code review TBD Not Started
Check/correct EOL on desk installed components to LF & verify other config files are not native. TBD/SPS Not Started
Test Case Development MAS In Work
Test Procedure Development MAS In Work
Test Case Reviews TBD Not Started
Test Procedure Reviews Notify SQA when this activity is complete. TBD Not Started
Software life cycle audits TBD Not Started
Traceaid Qualification TBD/SPS Not Started
ABC SCAT Qual TBD/SPS Not Started
Before the following can be done the above activities must be complete
Integration Review TBD/JEC Not Started
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and ABC Qual need to be completed
Formal build (including Conformity inspection) TBD/SPS/JEC Not Started
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence) N/A Not Started
Executable Object Code Analysis Review (Testing vs Release variant equivalence) N/A Not Started
Requirements Coverage Analysis TBD/SPS Not Started
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score SPS/JEC Not Started
Test Results Review TBD/JEC Not Started
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis SPS/TBD Not Started
Verification audit JEC Not Started
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive TBD/SPS Not Started
Report Documents TBD/SPS Not Started
- SLCECI TBD/SPS Not Started
- SLCECI review KKL Not Started
- SCI TBD/SPS Not Started
- SCI review KKL Not Started
Open Problem Reports List (after the final CCB) TBD Not Started
- SAS TBD/SPS Not Started
- SAS review KKL Not Started
- Publish Backend Docs: (update analysisStatus.txt) KKL Not Started
Update /11-14-verf-results/analysis/change-impact/analysisStatus.txt once verification completes on dependencies to include final change-impact analysis Update Change-Impact Analysis KKL Not Started
Software conformity audit JEC Not Started
Final Steps upon Verf Complete KKL Not Started