This page tracks development and verification activities and progress.

Charge Code

Server verification being tracked under Celestial in Project Manager.

Scope

Initial verification of gpio-nai-fpga for Program_Celestial

Activities

Task
Assignment
Status
Create and Initial Population of Certification Archive (If already created, just perform populate step.) HCM Done
Requirements Development JMD Done
Standards Change Analysis Complete before Initializing Status Files. JMD Done
Architecture Change Impact Analysis JMD Done
Requirements review MJF Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. JMD Done
Code review SPM Done
Test Case Development MJF Done
Test Procedure Development MJF Done
Test Reviews Notify SQA when this activity is complete. JMD Done
Software life cycle audits JEC Done
ABC SCAT Qual JMD Done
Before the following can be done the above activities must be complete
Integration Review JMD Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and ABC Qual need to be completed
Formal build (including Conformity inspection) JMD/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence) N/A
Executable Object Code Analysis Review (Testing vs Release variant equivalence) N/A
Requirements Coverage Analysis JMD Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score TBD/JEC Done
Test Results Review JMD Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis JMD Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive JMD Done
Report Documents
- SLCECI JMD Done
- SLCECI review KKL Done
- SCI JMD Done
- SCI review KKL Done
Open Problem Reports List (after the final CCB) JMD Done
- SAS JMD Done
- SAS review KKL Done
- Publish Backend Docs: (update analysisStatus.txt) KKL Done
Update /11-14-verf-results/analysis/change-impact/analysisStatus.txt once verification completes on dependencies to include final change-impact analysis Update Change-Impact Analysis JMK Done
Software conformity audit JEC Done