This project will establish a new verified baseline of Hosmer Boot Version 2.1.7 for the Hosmer_Program.
Boot Cert Process Activities
| Description | Assignee | Status | Due | Remarks |
| Requirements development | N/A | Done | N/A | |
| Requirements review | N/A | Done | N/A | |
| Code development | TBR | Done | N/A | |
| Code review | JON | Done | N/A | |
| Test case development | N/A | Done | N/A | |
| Test case review | N/A | Done | N/A | |
| Test procedure development | JON | Done | N/A | |
| Test procedure review | TBR | Done | N/A | |
| Software lifecycle audit | KL | Done | 2015-08-25 | |
| Requirements coverage analysis, including Traceaid qualification | JON | Done | N/A | |
| Conformity inspection - SQA build witness | JON/KL | Done | 2015-08-25 | |
| ABC qualification | TBR | Done | 2015-08-21 | |
| Integration review, including compiler assessment | JON/TBR/KL | Done | 2015-08-21 | |
| Run for score, including SQA witnessing & test results review | JON/TBR/KL | Done | 2015-08-25 | |
| Structural coverage analysis | JON | Done | 2015-08-26 | |
| Executable Object Code analysis | TBR | Done | 2015-08-24 | |
| Verification audit | KL | Done | 2015-08-27 | |
| Open problem reports list | JON | Done | 2015-08-24 | |
| Report Document Development (SLCECI) | JON | Done | 2015-08-27 | |
| Report Document Development (SCI) | JON | Done | 2015-08-27 | |
| Report Document Development (SAS) | JON | Done | 2015-08-27 | |
| Report Document Review | TBR | Done | 2015-08-28 | |
| Population of certification archive | JON | Done | 2015-08-28 | |
| Software conformity audit | KL | Done | 2015-08-31 | |
| Update latest-verified link on FTP server | JON | Done | 2015-08-31 |