I2C driver initial verification.

A DAL A project.

This page tracks development and verification activities and progress.


Activities

Outstanding Questions to Customer

  • TBD

Outstanding Requirement Tasks

  • TBD

Outstanding Code Tasks

  • TBD

Outstanding Test Tasks

  • TBD

Activities

Task
Assignment
Status
Notes
Create and Initial Population of Certification Archive (If already created, just perform populate step.) CP Done
Requirements Development CP Done
Standards Change Analysis Complete before Initializing Status Files. CP Done
Architecture Change Impact Analysis CP Done
Initialize Status Files Complete Standards Change Analysis first. CP Done
Requirements review SysPro Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. CP Done
Code review SysPro Done
Test Case Development SysPro Done
Test Procedure Development SysPro Done
Check/correct EOL on desk installed components to LF & verify other config files are not native. CP Done
Test Reviews Notify SQA when this activity is complete. SysPro Done
Software life cycle audits SQA Done
ABC SCAT Qual JD Done
Before the following can be done the above activities must be complete
Integration Review JD Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) JD/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence) N/A
Executable Object Code Analysis Review (Testing vs Release variant equivalence) N/A
Requirements Coverage Analysis JD Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score JD/JEC Done
Test Results Review JD Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis JD Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive KL Done
Report Documents
- SLCECI JMD/JMK Done
- SLCECI review KL Done
- SCI JMD/JMK Done
- SCI review KL Done
Open Problem Reports List (after the final CCB) JMD Done
- SAS JMD/JMK Done
- SAS review KL Done
- Publish Backend Docs: (update analysisStatus.txt) KL Done
Update /11-14-verf-results/analysis/change-impact/analysisStatus.txt once verification completes on dependencies to include final change-impact analysis Update Change-Impact Analysis JMK Done
Software conformity audit JEC Done
Final Steps upon Verf Complete KL Done