Kernel Granite Project
From DDCIDeos
Jump to navigationJump to search
Description
Run-for-score of Kernel Version 8.3.1, on customer hardware, for the Granite_Program.
Charge Codes:
- Deos Granite, 2120-470-638, kpverf
Regression results
- 20131103: All tests with expected results on DEBUG & RELEASE, except tpk167_down. PCR 10543 justifies the failure, and the fix on mainline passes on granite.
Upcoming Milestones
| Program | Milestones | Type | Stable Date | Ship Date | Cur. Date | Status
|
|---|
Task List Development
In addition to the following, there are also hypstart and integ tool changes required for the new features.
| Task | Assignee | Status | Estimate (days) |
Remarks |
|---|---|---|---|---|
| Intel Atom E3815 Errata analysis | RLR | In Work | See TBD |
Test Environment
| BSP Name | X9 Target Name(s) | Variant(s) | Comments |
|---|---|---|---|
| Granite | DeosGranite-1 or DeosGranite-2 | Release & Debug |
Test Environment Setup
Test global issues
TBD
Kernel Cert Work
| ABC Qual | Waiting to see if instrumented variants required | Not Started |
| Conformity Inspection | GK/KL | In Work |
| Run For Score | Not Started | |
| - Test Results Review | Not Started | |
| Before the following can be done the Run For Score needs to be completed | ||
|---|---|---|
| Structural coverage analysis | Not Started | |
| Verification audit | Not Started | |
| Before the following can be done the B-Tree analysis and Run For Score needs to be completed | ||
| Stack analysis | Not Started | |
| Stack analysis review | Not Started | |
| Before the following can be completed all of the above tasks need to be completed | ||
| Back end Docs | ||
| - SAS - Ready for review. | Not Started | |
| - SAS review | Not Started | |
| Populate the cert archive | Not Started | |
| Software conformity audit | Not Started | |