Activities

Task
Assignment
Status
Create and Initial Population of Certification Archive RLR Done
Requirements Development AM/RLR In Work
Standards Change Analysis RLR Done
Architecture Change Impact Analysis RLR In Work
Initialize Status Files TBD Not Started
Requirements review TBD Not Started
Code Development, i.e. trace tag insertion and additional test points as determined via test development. AM/RLR In Work
Code review TBD Not Started
Test Case Development TBD Not Started
Test Procedure Development TBD Not Started
Test Reviews TBD Not Started
Software life cycle audits SQA Not Started
Processor Compatibility Analysis TBD Not Started
Before the following can be done the above activities must be complete
Dynamic Dispatch aka V-Table Analysis (note: no review needed) TBD Not Started
Compiler Assessment TBD Not Started
Portal Analysis TBD Not Started
Portal Analysis Review TBD Not Started
Traceaid Qualification TBD Not Started
ABC SCAT Qual TBD Not Started
Initial Integration Checklist TBD Not Started
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) TBD Not Started
Complete Integration Checklist TBD Not Started
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis
- verify following task list matches kernel howto TBD Not Started
- linker invariants Analysis TBD Not Started
- Memory Barrier Analyses TBD Not Started
- ARM ldrex instruction Analysis TBD Not Started
Executable Object Code Analysis Review TBD Not Started
B-Tree analysis TBD Not Started
B-Tree analysis review TBD Not Started
Requirements Coverage Analysis TBD Not Started
MFS relocatable analysis TBD Not Started
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score TBD Not Started
Test Results Review TBD Not Started
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis TBD Not Started
Stack analysis TBD Not Started
Stack analysis review TBD Not Started
Confirm/update SCORE adarts SAS/stack usage analysis once the final kernel binaries have been built TBD Not Started
Verification audit SQA Not Started
Before the following can be completed all of the above tasks need to be completed
Processor Errata analysis TBD Not Started
Populate the cert archive TBD Not Started
Report Documents
- SLCECI TBD Not Started
- SLCECI review TBD Not Started
- SCI TBD Not Started
- SCI review TBD Not Started
Open Problem Reports List (after the final CCB) TBD Not Started
- SAS TBD Not Started
- SAS review TBD Not Started
- Publish Backend Docs: (update analysisStatus.txt) TBD Not Started
Software conformity audit SQA Not Started
Final Steps upon Verf Complete TBD Not Started