MTL Multicore

From DDCIDeos
Jump to navigationJump to search

Mailbox Transport Library (MTL) updates for Harrys_Program.

A DAL A project.

This page tracks development and verification activities and progress.

The project calls for Mailbox Transport Library to be extended with the following for Deos Harrys Verf Complete:

  • ARM Support
  • Removal of depreciated types
  • cd and fp xml support for Open Arbor
  • Test suite updates to the latest test utilities

Deos Harrys Verf Complete is unverified.

The final release will be verified (at least for ARM).


Activities

Outstanding Questions to Customer

  • None

Outstanding Requirement Tasks

  • All

Outstanding Code Tasks

  • Initial implementations of the APIs have been added to MTL.

Outstanding Test Tasks

  • Develop new test cases
  • Develop preliminary test procedures and complete


Task
Assignment
Status
Requirements Development MDV Done
Standards Change Analysis MDV Done
Architecture Change Impact Analysis MDV Done
Initialize Status Files MDV Done
Requirements review JK Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. MDV Done
Code review JK Done
Test Case Development JK Done
Test Procedure Development JK Done
Test Reviews Notify SQA when this activity is complete. MDV Done
Software life cycle audits JEC Done
ABC SCAT Qual MDV Done
Before the following can be done the above activities must be complete
Integration Review MDV/JEC Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) MDV/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence)
Executable Object Code Analysis Review (Testing vs Release variant equivalence)
Requirements Coverage Analysis MDV Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score MDV/JEC Done
Test Results Review MDV Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis MDV Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Report Documents
- SLCECI JK Done
- SLCECI review MS Done
- SCI JK Done
- SCI review MS Done
- Open Problem Reports List MDV Done
- SAS JK Done
- SAS review MS Done
Populate the cert archive MDV Done
Software conformity audit JEC Done