MTL Multicore
From DDCIDeos
Jump to navigationJump to search
Mailbox Transport Library (MTL) updates for Harrys_Program.
A DAL A project.
This page tracks development and verification activities and progress.
The project calls for Mailbox Transport Library to be extended with the following for Deos Harrys Verf Complete:
- ARM Support
- Removal of depreciated types
- cd and fp xml support for Open Arbor
- Test suite updates to the latest test utilities
Deos Harrys Verf Complete is unverified.
The final release will be verified (at least for ARM).
Useful Links
- Query of all outstanding PCRs
- Query of open Rqts/Code PCRs (PCRs with requirements/code work assigned).
- Query of open test PCRs (PCRs with test work assigned).
- mainline review status
Activities
Outstanding Questions to Customer
- None
Outstanding Requirement Tasks
- All
Outstanding Code Tasks
- Initial implementations of the APIs have been added to MTL.
Outstanding Test Tasks
- Develop new test cases
- Develop preliminary test procedures and complete
| Requirements Development | MDV | Done |
| Standards Change Analysis | MDV | Done |
| Architecture Change Impact Analysis | MDV | Done |
| Initialize Status Files | MDV | Done |
| Requirements review | JK | Done |
| Code Development, i.e. trace tag insertion and additional test points as determined via test development. | MDV | Done |
| Code review | JK | Done |
| Test Case Development | JK | Done |
| Test Procedure Development | JK | Done |
| Test Reviews Notify SQA when this activity is complete. | MDV | Done |
| Software life cycle audits | JEC | Done |
| ABC SCAT Qual | MDV | Done |
| Before the following can be done the above activities must be complete | ||
|---|---|---|
| Integration Review | MDV/JEC | Done |
| Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed | ||
| Formal build (including Conformity inspection) | MDV/JEC | Done |
| Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task. | ||
| Executable Object Code Analysis (Testing vs Release variant equivalence) | ||
| Executable Object Code Analysis Review (Testing vs Release variant equivalence) | ||
| Requirements Coverage Analysis | MDV | Done |
| Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful. | ||
| Run For Score | MDV/JEC | Done |
| Test Results Review | MDV | Done |
| Before the following can be done the Run For Score needs to be completed | ||
| Structural coverage analysis | MDV | Done |
| Verification audit | JEC | Done |
| Before the following can be completed all of the above tasks need to be completed | ||
| Report Documents | ||
| - SLCECI | JK | Done |
| - SLCECI review | MS | Done |
| - SCI | JK | Done |
| - SCI review | MS | Done |
| - Open Problem Reports List | MDV | Done |
| - SAS | JK | Done |
| - SAS review | MS | Done |
| Populate the cert archive | MDV | Done |
| Software conformity audit | JEC | Done |