Maple MAL Verification Timesheet code: Project: 2120-320-605, Task: MAL 2.99

Be a Maintainer

  • Fire up the Cygwin "Fourpeaks" install path, and select the following packages
    • Deos-Bundles, deos-maintainer-tools
    • Deos-Customers, customer-maple
    • Deos, deos653p 1-runtime

Activities

Verification Effort Estimate Summary

  • Note To convert effort estimates in hours to calendar days, use this formula:
 days = task_estimate_hours * 0.5

Rationale: An Engineer's time-on-task will likely be no higher than 25%. That is, it will take him 4 times longer to complete when measured in calendar time. We also assume each calendar day has 8 working hours available. Thus, if an Engineer is given a task that is estimated to require 2 hours of effort, it will require 1 calendar day to complete.

Task Estimate (Hours) Remarks
Verify Maple MAL 291 Bill Done


For the table below, the Estimate column reflects effort to be spent once verification activities begin.

Description Assignee Status Estimate (Hours) Remarks
Requirements Development MD Done 40
Requirements Review Sergio Done 20 Required with independence per DDC-I PSAC.
Code Development MD Done 0 Verification driven code changes are to be charged against the verification activity that caused the change, e.g. Requirements Review
Code Review N/A N/A 0 Not required for DAL D.
Test Case Development Sergio Done 40 Author independence not required for DAL D
Test Case Review MD Done 20 Review Independence not required for DAL D
Test Procedure Development Sergio Done 120
Test Procedure Review N/A N/A 0 Not required for DAL D.
Executable Object Code Analysis N/A N/A 0 Not required for DAL D.
Software Lifecycle Audit SQA Done 8 [2014-225] and [2014-239] - PCR [9353]
Document Build Environment MD Done 1 This took more like 4 hours.
Document Test Environment MD Done 1
Requirements Coverage Analysis, including Traceaid Qualification MD Done 4 Trace between Requirements and Test Cases only
Compiler Assessment N/A N/A 0 Not required for DAL D.
ABC Tool Qualification N/A N/A 0 Not required for DAL D.
Structural Coverage Analysis N/A N/A 0 Not required for DAL D.
Conformity Inspection - SQA Build Witness SQA, MD Done 2 Scheduled for 2014-Aug-06
Integration Review MD Done 4 Scheduled for 2014-Aug-06
Run for Score, including SQA Witnessing, and Test Results Review SQA, MD Done 2 Scheduled for 2014-Aug-06
Verification Audit KL Done 4
Open Problem Reports List MD Done 4
Report Document Development (SLCECI, SCI, SAS) MD Done 8
Report Document Review ML Done 2 ML: Michael Landreth
Population of Certification Archive (PCA) MD Done 8
Software Conformity Audit SQA Done 4 SQA == Kelly Leonard