Math library updates for Desert_Eagle_Program.

A DAL A project.

This page tracks development and verification activities and progress.

The project calls for Math to be extended with the following APIs for Deos_Desert_Eagle_D2_Release:

  • drem() & dremf()
  • finite()
  • fmax & fmaxf()
  • fmin & fminf()
  • isfinite()
  • remainder() & remainderf()

Deos_Desert_Eagle_D2_Release is unverified.

The final release will be verified (at least for ARM).


Activities

Outstanding Questions to Customer

  • None

Outstanding Requirement Tasks

  • All

Outstanding Code Tasks

  • Initial implementations of the APIs have been added to Math.

Outstanding Test Tasks

  • Develop new test cases
  • Develop preliminary test procedures and complete


Task
Assignment
Status
Requirements Development JON Done
Standards Change Analysis JON Done
Architecture Change Impact Analysis JON Done
Initialize Status Files JON Done
Requirements review NL Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. JON Done
Code review NL Done
Test Case Development DED Done
Test Procedure Development DED Done
Test Reviews Notify SQA when this activity is complete. MAS Done
Software life cycle audits JEC Done
ABC SCAT Qual JON Done
Before the following can be done the above activities must be complete
Integration Review JON Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) JEC/JON Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence)
Executable Object Code Analysis Review (Testing vs Release variant equivalence)
Requirements Coverage Analysis JON Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score JON Done
Test Results Review JON Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis JON Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Report Documents
- SLCECI JON Done
- SLCECI review KL Done
- SCI JON Done
- SCI review KL Done
- Open Problem Reports List JON Done
- SAS JON Done
- SAS review KL Done
Populate the cert archive JON Done
Software conformity audit JEC Done