SAL Socket API Library
From DDCIDeos
Jump to navigationJump to search
Socket API Library (SAL) updates for Desert Eagle. This is a follow on to the SAL Indie project.
A DAL A project.
This page tracks development and verification activities and progress.
The project calls for Socket API Library to be extended with the following:
- TBD
Deos Harrys Verf Complete is unverified.
The final release will be verified (at least for ARM).
Useful Links
- Query of all outstanding PCRs
- Query of open Rqts/Code PCRs (PCRs with requirements/code work assigned).
- Query of open test PCRs (PCRs with test work assigned).
- mainline review status
Activities
Outstanding Questions to Customer
- TBD
Outstanding Requirement Tasks
- TBD
Outstanding Code Tasks
- TBD
Outstanding Test Tasks
- TBD
| Create and Initial Population of Certification Archive (If already created, just perform populate step.) | JJK | Done | |
| Requirements Development | JJK | Done | |
| Standards Change Analysis Complete before Initializing Status Files. | RLF | Done | |
| Architecture Change Impact Analysis | RLF | Done | |
| Initialize Status Files Complete Standards Change Analysis first. | JJK | Done | Requirements/code energized. Test/Analysis have not been |
| Requirements review | RLF | Done | |
| Code Development, i.e. trace tag insertion and additional test points as determined via test development. | JJK | Done | |
| Code review | RLF | Done | |
| Test Case Development | MAS | Done | |
| Test Procedure Development | MAS | Done | |
| Test Reviews Notify SQA when this activity is complete. | DED | Done | |
| Software life cycle audits | SQA | Done | |
| ABC SCAT Qual | JJK | Done | |
| Before the following can be done the above activities must be complete | |||
|---|---|---|---|
| Integration Review | JJK | Done | |
| Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed | |||
| Formal build (including Conformity inspection) | JJK/SQA | Done | |
| Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task. | |||
| Executable Object Code Analysis (Testing vs Release variant equivalence) | NA | ||
| Executable Object Code Analysis Review (Testing vs Release variant equivalence) | NA | ||
| Requirements Coverage Analysis | JJK | Done | |
| Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful. | |||
| Run For Score | JJK/JEC | Done | |
| Test Results Review | JJK | Done | |
| Before the following can be done the Run For Score needs to be completed | |||
| Structural coverage analysis | JJK | Done | |
| Verification audit | JEC | Done | |
| Before the following can be completed all of the above tasks need to be completed | |||
| Populate the cert archive | KKL | Done | |
| Report Documents | |||
| - SLCECI | JJK | Done | |
| - SLCECI review | KKL | Done | |
| - SCI | JJK | Done | |
| - SCI review | KKL | Done | |
| Open Problem Reports List (after the final CCB) | JJK | Done | |
| - SAS | JJK | Done | |
| - SAS review | KKL | Done | |
| - Publish Backend Docs: (update analysisStatus.txt) | KKL | Done | |
| Software conformity audit | JEC | Done | |
| Final Steps upon Verf Complete | KKL | Done | |