ADA-RTS verification for Tostones3 Program.
A DAL A project.
This page tracks development, verification activities and progress of the rts component.
Charge Code
Server verification being tracked under Tostones3 in Project Manager.
Useful Links
- Query of all outstanding PCRs
- Query of open Rqts/Code PCRs (PCRs with requirements/code work assigned).
- Query of open test PCRs (PCRs with test work assigned).
- mainline review status
Scope
Initial verification of ADA-RTS for Program_Tostones
Activities
| Create and Initial Population of Certification Archive (If already created, just perform populate step.) | JEC | Done |
| Requirements Development | JON | Done |
| Standards Change Analysis | JON | Done |
| Architecture Change Impact Analysis | JON | Done |
| Initialize Status Files | JON | Done |
| Requirements review | MS | Done |
| Code Development, i.e. trace tag insertion and additional test points as determined via test development. | JON | Done |
| Code review | RLF | Done |
| Test Case Development | MS | Done |
| Test Procedure Development | MS/JON | Done |
| Test Reviews Notify SQA when this activity is complete. | MS/JON/RLF | Done |
| Software life cycle audits | JEC | Done |
| ABC SCAT Qual | JON | Done |
| Before the following can be done the above activities must be complete | ||
|---|---|---|
| Integration Review | JON | Done |
| Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and ABC Qual need to be completed | ||
| Formal build (including Conformity inspection) | JON | Done |
| Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task. | ||
| Requirements Coverage Analysis | JON | Done |
| Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful. | ||
| Run For Score Note:Audit cannot be completed until Requirement Coverage Analysis is completed. | JON/JEC | Done |
| Test Results Review | JON | Done |
| Before the following can be done the Run For Score needs to be completed | ||
| Structural coverage analysis | JON | Done |
| Verification audit | JEC | Done |
| Before the following can be completed all of the above tasks need to be completed | ||
| Populate the cert archive | JON | Done |
| Report Documents | ||
| - SLCECI | JON | Done |
| - SLCECI review | KKL | Done |
| - SCI | JON | Done |
| - SCI review | KKL | Done |
| Open Problem Reports List (after the final CCB) | JON | Done |
| - SAS | JON | Done |
| - SAS review | KKL | Done |
| - Publish Backend Docs: (update analysisStatus.txt) | KKL | Done |
| Software conformity audit | JEC | Done |