Milestones Due Date Estimated Delivery Delivered Percentage Complete
[1] Beta Release 01-Jan-08 30-Jan-08 TBD 50%


[1] Beta Release

Task Dependency Assignee Original Estimate Elapsed Remaining
1.0 Discovery Hardware @Tigard Office Ryan 16 12.5 0
1.1 Implement Fix 1.0 Ryan 16 5 0
1.2 Update release notes 1.1 Matt 3 1 0
1.3 Build kernel distribution 1.1 Matt 4 4 0
1.4 Ad Hoc test on Geode, etc. 1.1 Matt Ryan 8 6 0
1.5 Mark stable and release 1.1 Matt 0 1 0
Totals 194 29.5 0