Target Data Loader Project

From DDCIDeos
Jump to navigationJump to search

The Target Data Loader (TDL) is a collection of software components that implement a subset of the ARINC 615A and ARINC 615-3 loading protocols. It consists of a Main Process, Integrity Library and Custom Library. It also uses the TFTP Library. All components are DO-178B level E except for the Integrity Library, which is level A.

Current activities include bringing all components up-to-date for their first release by DDC-I. The development of a custom library for the Hosmer program is also part of this project.

Charge Code

Harrys Program

Activities

Description Assignee Status
Requirements Development MDV Done
Standards Change Analysis MDV Done
Architecture Change Impact Analysis MDV Done
Initialize Status Files MDV Done
Requirements review CP Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. MDV Done
Code review (awaiting accept of code checklist) CP Done
Test Case Development CP Done
Test Procedure Development MDV Done
Test Reviews Notify SQA when this activity is complete. MDV, CP Done
Software life cycle audits JEC Done
ABC SCAT Qual MDV Done
Before the following can be done the above activities must be complete
Integration Review MDV Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and ABC Qual need to be completed
Formal build (including Conformity inspection) MDV Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence)
Executable Object Code Analysis Review (Testing vs Release variant equivalence)
Requirements Coverage Analysis MDV Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score MDV/JEC Done
Test Results Review MDV Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis MDV Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Report Documents
- Open Problem Reports List RDR/MDV Done
- Create Backend Docs: SLCECI, SCI and SAS RDR/MDV Done
- Review and Publish Backend Docs: (update analysisStatus.txt) MS Done
Populate the cert archive MDV Done
Software conformity audit JEC Done