Time Jupiter

From DDCIDeos
Jump to navigationJump to search

Time verification for ARM, PPC and X86 using multicore.

A DAL A project.

This page tracks development and verification activities and progress.


Scope

Time (deos-time) is a new component which is providing a limited set of time related function allowing applications to read the current time from the PAL, set timezone, show time in various ways and more.

Time is supported for ARM, PPC and X86, using target boards that actually provide the current time. All the qemus do that, and also many newer boards,

To work, the time-prl component must be included, and the process threads that wish to access the time information must be privileged to do so, and this is done with xml-additions.

Activities

Outstanding Requirement Tasks

  • None. Requirements document has been created.

Status files for Requirements, Code and Test have been created.

Outstanding Code Tasks

  • None. Code completed

Outstanding Test Tasks

  • Test cases and procedures shall be created.

4 test programs exist which can be used as basis for the to-be-developed test cases/procedures.


Task
Assignment
Status
Create and Initial Population of Certification Archive (If already created, just perform populate step.) MV/RDR Done
Requirements Development MV Done
Standards Change Analysis MV/RDR Done
Architecture Change Impact Analysis MV/RDR Done
Initialize Status Files RDR Done
Requirements review RDR Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. MV Done
Code review RDR Done
Test Case Development MAS/RDR Done
Test Procedure Development MAS/RDR Done
Test Reviews Notify SQA when this activity is complete. DED/MAS Done
Software life cycle audits SQA Done
ABC SCAT Qual MAS Done
Before the following can be done the above activities must be complete
Integration Review MAS/JEC Done
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) MAS/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence)
Executable Object Code Analysis Review (Testing vs Release variant equivalence)
Requirements Coverage Analysis MAS Done
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score MAS Done
Test Results Review MAS Done
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis MAS Done
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive MAS Done
Report Documents
- SLCECI MAS Done
- SLCECI review KKL Done
- SCI MAS Done
- SCI review KKL Done
Open Problem Reports List (after the final CCB) MAS Done
- SAS MAS Done
- SAS review KKL Done
- Publish Backend Docs: (update analysisStatus.txt) KKL Done
Software conformity audit JEC Done
Final Steps upon Verf Complete MAS/JEC Done