TrickyFish-BSP (includes deosboot and uboot) verification for TrickyFish Program.

A DAL D project.

This page tracks development and verification activities and progress.

Charge Code

Verification being tracked under Tricky Fish in Project Manager.

TODO - Update Links

Scope

Initial verification of TrickyFish-BSP for Program_TrickyFish

Activities

TODO

  1. Verify the list of tasks are correct (e.g. analyses).
  2. Verify assignments.


Task
Assignment
Status
Create and Initial Population of Certification Archive (If already created, just perform populate step.) JEC Done
Requirements Development ALR Done
Architecture Change Impact Analysis emora Done
Standards Change Analysis emora Done
Initialize Status Files sleon Done
Requirements review - Independence required (DDCI PSAC App D, but not DO-178c). emora, sleon, ifernandez Done
Code Development - No trace tags in code required. emora, sleon Done
Check/correct EOL on desk installed components to LF & verify other config files are not native. sleon Done
Test Case Development ifernandez, sleon, lcarrillo Done
Test Procedure Development ifernandez, sleon, lcarrillo Done
Software life cycle audits JEC Done
Before the following can be done the above activities must be complete
Integration Review drafted ifernandez Done
Before the following can be done, Traceaid needs to be qualified and the Requirements Coverage analysis' traceability needs to be confirmed.
Formal build (including Conformity inspection) ifernandez/JEC Done
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis.
Executable Object Code Analysis (Testing vs Release variant equivalence) ifernandez Done
Stack Usage Analysis sleon Done
Requirements Coverage Analysis ifernandez Done
Before the following can be completed all of the above analyses need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score ifernandez/JEC Done
Test Results Review ifernandez Done
Before the following can be completed all of the above tasks need to be completed
Verification audit JEC Done
Before the following can be completed all of the above tasks need to be completed
Populate the cert archive ifernandez Done
Report Documents
- SLCECI sleon Done
- SCI sleon Done
Open Problem Reports List (after the final CCB) sleon Done
- SAS sleon Done
- Publish Backend Docs: (update analysisStatus.txt) KKL Done
Software conformity audit JEC Done
Final Steps upon Verf Complete KKL Done