Vfile Kismet
From DDCIDeos
Jump to navigationJump to search
Vfile verification for Kismet.
A DAL A project.
This page tracks development and verification activities and progress.
Charge Code
???
Useful Links
- Query of all outstanding PCRs
- Query of all Rqts/Code PCRs (PCRs with requirements/code work assigned).
- Query of open Test PCRs (PCRs with test work assigned).
- Mainline Review Status
Scope
Verification of Vfile for Kismet.
Activities
| Create and Initial Population of Certification Archive (If already created, just perform populate step.) | CP | Done | |
| Requirements Development | CP | In Work | |
| Standards Change Analysis | CP | In Work | |
| Architecture Change Impact Analysis | CP | In Work | |
| Initialize Status Files | CP | In Work | |
| Requirements review | DED | In Work | |
| Code Development, i.e. trace tag insertion and additional test points as determined via test development. | CP | In Work | |
| Code review | TBD | Not Started | |
| Test Case Development | TBD | Not Started | |
| Test Procedure Development | TBD | Not Started | |
| Test Reviews | TBD | Not Started | |
| Software life cycle audits | SQA | Not Started | |
| Traceaid Qualification | TBD | Not Started | |
| ABC SCAT Qual | TBD | Not Started | |
| Before the following can be done the above activities must be complete | |||
|---|---|---|---|
| Initial Integration Checklist | TBD | Not Started | |
| Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed | |||
| Formal build (including Conformity inspection) | TBD | Not Started | |
| Complete Integration Checklist | TBD | Not Started | |
| Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task. | |||
| Executable Object Code Analysis | N/A | N/A | |
| Requirements Coverage Analysis | TBD | Not Started | |
| Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful. | |||
| Run For Score | TBD | Not Started | |
| Test Results Review | TBD | Not Started | |
| Before the following can be done the Run For Score needs to be completed | |||
| Structural coverage analysis | TBD | Not Started | |
| Verification audit | SQA | Not Started | |
| Before the following can be completed all of the above tasks need to be completed | |||
| Populate the cert archive | TBD | Not Started | |
| Report Documents | |||
| - SLCECI | TBD | Not Started | |
| - SLCECI review | TBD | Not Started | |
| - SCI | TBD | Not Started | |
| - SCI review | TBD | Not Started | |
| Open Problem Reports List (after the final CCB) | TBD | Not Started | |
| - SAS | TBD | Not Started | |
| - SAS review | TBD | Not Started | |
| - Publish Backend Docs: (update analysisStatus.txt) | TBD | Not Started | |
| Software conformity audit | SQA | Not Started | |
| Final Steps upon Verf Complete | TBD | Not Started | |