The SLS_Program desires to use fixed budget only (no slack) for their network applications. In order to support this, the process-based Pro100 network driver needs to be updated to use short-duration waits for events and semaphores instead of indefinite waits (which are a better choice for slack). This will be accomplished by receiving a configuration value from the Network process that determines which type of wait to use. The desired behavior will be specified by the user in the network configuration file.
News
- 12-5-2007: Support for short-duration waits has been added per PCR 4706.
Tasks
Initial Budget: $67,183
TTD: $38,092
Current ETC: $3,424
Current EAC: $41,516
| Delivery | Due Date | Estimated Delivery | Delivered | Percentage Complete |
|---|---|---|---|---|
| [1] Certification Candidate Release | 02-Mar-08 | 06-Jun-08 | 05-Jun-08 | 100% |
| [2] Software Accomplishment Summary Release | 29-Mar-08 | 16-Jun-08 | 23-Jun-08 | 100% |
Delivery [1] Certification Candidate Release
- Feature Description: Sufficient verification steps complete to achieve high confidence executables will not need further changes.
| Task | Dependency | Assignee | Risk | Original Estimate | Current Estimate | Elapsed | Remaining |
|---|---|---|---|---|---|---|---|
| 1.1 Requirements development | N/A | JBR | Change in customer requirements | 40 | 40 | 40 | 0 |
| 1.2 Code development | 1.1 | JBR | None | 60 | 40 | 39 | 0 |
| 1.3 Test case development | 1.1 | Uzeir | Resource availability | 20 | 20 | 20 | 0 |
| 1.4 Test procedure development | 1.1 | Uzeir | Resource availability | 177 | 177 | 177 | 0 |
| 1.5 Requirements review | 1.1 | Uzeir | Resource availability | 24 | 24 | 5 | 0 |
| 1.6 Code review | 1.2 | Uzeir | Resource availability | 24 | 24 | 0 | 0 |
| 1.7 Test case review | 1.3 | JBR | None | 16 | 16 | 1 | 0 |
| 1.8 Test procedure review | 1.4 | JBR | None | 16 | 16 | 0 | 0 |
| 1.9 Software life cycle audit | 1.8 | Kelly Leonard | None | 16 | 16 | 8 | 0 |
| Totals | 393 | 373 | 290 | 0 | |||
Delivery [2] Software Accomplishment Summary Release
- Feature Description: Indicates all verification steps complete.
| Task | Dependency | Assignee | Risk | Original Estimate | Current Estimate | Elapsed | Remaining |
|---|---|---|---|---|---|---|---|
| 2.1 Requirements coverage analysis | 1.2 | JBR | None | 16 | 16 | 2 | 0 |
| 2.2 Conformity inspection - SQA build Witness | 2.1 | Kelly Leonard | None | 8 | 8 | 4 | 0 |
| 2.3 SCAT/ABC qualification (v4.2.0 is PPC only) | N/A | Uzeir | Resource availability | 8 | 8 | 4 | 0 |
| 2.4 Integration review | 2.2, 2.3 | Kelly Leonard | None | 16 | 16 | 16 | 0 |
| 2.5 Run for score, including SQA witnessing, and test results review | 2.4 | Uzeir and Kelly Leonard | Resource availability | 8 | 8 | 8 | 0 |
| 2.6 Structural coverage analysis | 2.5 | Uzeir and JBR | Resource availability | 32 | 32 | 29 | 0 |
| 2.7 Verification audit | 2.6 | Kelly Leonard | None | 8 | 8 | 4 | 0 |
| 2.8 Certification documents: SAS, SLCECI, SCI | 2.6 | JBR | None | 24 | 24 | 7 | 0 |
| 2.9 Population of certification archive (PCA) | 2.8 | JBR | None | 8 | 8 | 4 | 0 |
| 2.10 Software conformity audit | 2.9 | Kelly Leonard | None | 8 | 8 | 6 | 0 |
| Totals | 136 | 136 | 80 | 0 | |||