Pro100 Project

From Deos
Jump to navigationJump to search


This effort is in support of the SLS_Program.

Description

The SLS_Program desires to use fixed budget only (no slack) for their network applications. In order to support this, the process-based Pro100 network driver needs to be updated to use short-duration waits for events and semaphores instead of indefinite waits (which are a better choice for slack). This will be accomplished by receiving a configuration value from the Network process that determines which type of wait to use. The desired behavior will be specified by the user in the network configuration file.

News

  • 12-5-2007: Support for short-duration waits has been added per PCR 4706.

Tasks

Initial Budget: $67,183

TTD: $38,092

Current ETC: $3,424

Current EAC: $41,516


Delivery Due Date Estimated Delivery Delivered Percentage Complete
[1] Certification Candidate Release 02-Mar-08 06-Jun-08 05-Jun-08 100%
[2] Software Accomplishment Summary Release 29-Mar-08 16-Jun-08 23-Jun-08 100%


Delivery [1] Certification Candidate Release

  • Feature Description: Sufficient verification steps complete to achieve high confidence executables will not need further changes.

Review status summary

Task Dependency Assignee Risk Original Estimate Current Estimate Elapsed Remaining
1.1 Requirements development N/A JBR Change in customer requirements 40 40 40 0
1.2 Code development 1.1 JBR None 60 40 39 0
1.3 Test case development 1.1 Uzeir Resource availability 20 20 20 0
1.4 Test procedure development 1.1 Uzeir Resource availability 177 177 177 0
1.5 Requirements review 1.1 Uzeir Resource availability 24 24 5 0
1.6 Code review 1.2 Uzeir Resource availability 24 24 0 0
1.7 Test case review 1.3 JBR None 16 16 1 0
1.8 Test procedure review 1.4 JBR None 16 16 0 0
1.9 Software life cycle audit 1.8 Kelly Leonard None 16 16 8 0
Totals 393 373 290 0

Delivery [2] Software Accomplishment Summary Release

  • Feature Description: Indicates all verification steps complete.
Task Dependency Assignee Risk Original Estimate Current Estimate Elapsed Remaining
2.1 Requirements coverage analysis 1.2 JBR None 16 16 2 0
2.2 Conformity inspection - SQA build Witness 2.1 Kelly Leonard None 8 8 4 0
2.3 SCAT/ABC qualification (v4.2.0 is PPC only) N/A Uzeir Resource availability 8 8 4 0
2.4 Integration review 2.2, 2.3 Kelly Leonard None 16 16 16 0
2.5 Run for score, including SQA witnessing, and test results review 2.4 Uzeir and Kelly Leonard Resource availability 8 8 8 0
2.6 Structural coverage analysis 2.5 Uzeir and JBR Resource availability 32 32 29 0
2.7 Verification audit 2.6 Kelly Leonard None 8 8 4 0
2.8 Certification documents: SAS, SLCECI, SCI 2.6 JBR None 24 24 7 0
2.9 Population of certification archive (PCA) 2.8 JBR None 8 8 4 0
2.10 Software conformity audit 2.9 Kelly Leonard None 8 8 6 0
Totals 136 136 80 0