Mailbox Transport Library (MTL) updates for Desert Eagle. This is a follow on to the MTL Multicore project.
A DAL A project.
This page tracks development and verification activities and progress.
The project calls for Mailbox Transport Library to be extended with the following for Deos Harrys Verf Complete:
- TBD
Deos Harrys Verf Complete is unverified.
The final release will be verified (at least for ARM).
Useful Links
- Query of all outstanding PCRs
- Query of open Rqts/Code PCRs (PCRs with requirements/code work assigned).
- Query of open test PCRs (PCRs with test work assigned).
- mainline review status
Activities
Outstanding Questions to Customer
- NA
Outstanding Requirement Tasks
- NA
Outstanding Code Tasks
- NA
| Create and Initial Population of Certification Archive (If already created, just perform populate step.) | JJK | Done |
| Requirements Development | JJK | Done |
| Standards Change Analysis Complete before Initializing Status Files. | JJK | Done |
| Architecture Change Impact Analysis | JJK | Done |
| Initialize Status Files Complete Standards Change Analysis first. | MAS | Done |
| Requirements review | MAS | Done |
| Code Development, i.e. trace tag insertion and additional test points as determined via test development. | JJK | Done |
| Code review | MAS | Done |
| Test Case Development | MAS | Done |
| Test Procedure Development | MAS | Done |
| Test Reviews Notify SQA when this activity is complete. | DED | Done |
| Software life cycle audits | SQA | Done |
| ABC SCAT Qual | JJK | Done |
| Before the following can be done the above activities must be complete | ||
|---|---|---|
| Integration Review | JJK | Done |
| Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed | ||
| Formal build (including Conformity inspection) | JJK/JEC | Done |
| Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task. | ||
| Executable Object Code Analysis (Testing vs Release variant equivalence)- NA | JJK | Done |
| Executable Object Code Analysis Review (Testing vs Release variant equivalence)-NA | JJK | Done |
| Requirements Coverage Analysis | JJK | Done |
| Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful. | ||
| Run For Score | JJK/JEC | Done |
| Test Results Review | JJK | Done |
| Before the following can be done the Run For Score needs to be completed | ||
| Structural coverage analysis | JJK | Done |
| Verification audit | SQA | Done |
| Before the following can be completed all of the above tasks need to be completed | ||
| Populate the cert archive | JJK | Done |
| Report Documents | ||
| - SLCECI | JJK | Done |
| - SLCECI review | KL | Done |
| - SCI | JJK | Done |
| - SCI review | KL | Done |
| Open Problem Reports List (after the final CCB) | JJK | Done |
| - SAS | JJK | Done |
| - SAS review | KL | Done |
| - Publish Backend Docs: (update analysisStatus.txt) | KL | Done |
| Software conformity audit | JEC | Done |
| Final Steps upon Verf Complete | JJK | Done |