Time-prl verification for ARM, PPC and X86 using multicore.

Component has been Deprecated -- See Time_Jupiter

A DAL A project.

This page tracks development and verification activities and progress.



Scope

Time-prl is a new component which is supporting the time component as a process resource library gaining access to Deos system time via the target board's PAL. All the qemus' PALs support this, and also many newer boards,

The time-prl component requires the calling process to be privileged to modify the time-prl information, and this is done with xml-additions for the calling process.

Activities

Outstanding Requirement Tasks

  • None. Requirements document for time-prl has been created.

Status file for Requirements, Code and Test have been created.

Outstanding Code Tasks

  • None. Code completed

Outstanding Test Tasks

  • The creation of test cases and following the test procedures.

4 ad hoc test programs exist which can be used as basis for the to-be-developed test cases/procedures.


Task
Assignment
Status
Requirements Development TBR Done
Standards Change Analysis TBD No
Initialize Status Files TBR Done
Requirements review MAS Done
Code Development, i.e. trace tag insertion and additional test points as determined via test development. TBR Done
Code review MAS In Work
Test Case Development MAS In Work
Test Procedure Development DED No
Test Reviews DED/MAS No
Software life cycle audits SQA No
ABC SCAT Qual TBR No
Before the following can be done the above activities must be complete
Integration Review TBR/JEC No
Before the following can be done the Requirements Coverage analysis' traceability needs to be confirmed and SCAT Qual need to be completed
Formal build (including Conformity inspection) TBR/JEC No
Before the following can be done the Formal build needs to be completed. Each executable object code analysis has an analysis and review task.
Executable Object Code Analysis (Testing vs Release variant equivalence)
Executable Object Code Analysis Review (Testing vs Release variant equivalence)
Requirements Coverage Analysis TBR No
Before the following can be completed all of the above analysis need to be completed. The RFS was completed with the expectation the analysis above will be successful.
Run For Score TBR No
Test Results Review ? No
Before the following can be done the Run For Score needs to be completed
Structural coverage analysis TBR No
Verification audit JEC No
Before the following can be completed all of the above tasks need to be completed
Report Documents
- SLCECI JON? Not Started
- SLCECI review TBD Not Started
- SCI JON? Not Started
- SCI review TBD Not Started
- Open Problem Reports List JON? Not Started
- SAS JON? Not Started
- SAS review TBD Not Started
Populate the cert archive JON? Not Started
Software conformity audit JEC Not Started